Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
New Detached ADU in Richland Hills, TX: What It Takes and What It Costs
A new detached ADU in Richland Hills typically runs $45,000 to $130,000 for a standard single-story unit, and most projects take four to seven months from permit submission to final inspection. A detached ADU is a separate, self-contained dwelling on the same lot as the main house: its own foundation, walls, roof, kitchen, bath, and utility connections, built to the same code as the home you live in. Call (855) 912-5373 and we’ll walk your lot, check your setbacks, and give you a written line-item estimate before you commit to anything.
How a Detached ADU Gets Built: Stage by Stage

Every detached ADU follows the same broad sequence, but the timing on your lot depends on how much site work the unit needs before framing starts. Here’s what actually happens, and what you decide along the way.
Stage 1: Site walk and feasibility (week 1)
We start by measuring your lot against Richland Hills’ setback and lot-coverage requirements, because the buildable envelope, not your budget, is what sets the real maximum footprint. You decide the unit size and whether you want a one-bedroom or a two-bedroom layout. This is also when we look at where the main house’s sewer, water, and electrical service sit, since distance from those points drives the utility trench cost.
Stage 2: Design and permitting (weeks 2 through 8 or longer)
Drawings go to the city for plan review, and this is the stage that moves fastest or slowest depending on completeness. You approve the floor plan, exterior finish package, and roof pitch here, then we submit. Detached structures get their own permit in Richland Hills, separate from any work on the main house, so the review clock starts fresh for the ADU even if you’ve pulled permits recently.
Stage 3: Site prep, utilities, and foundation (weeks 9 through 13)
We trench for water, sewer, and electrical, then form and pour the slab. On the clay soils common in this part of Tarrant County, the engineer’s foundation design matters more than usual: post-tensioned slabs are typical, and you’ll see the difference in the first hot, dry summer after the pour. You decide slab versus a raised pier-and-beam floor, which is mostly a cost trade-off unless the unit sits on a low spot.
Stage 4: Framing, envelope, and rough-ins (weeks 14 through 21)
Walls go up, the roof goes on, windows and exterior doors set, and plumbing and electrical rough-in run through the walls. You pick exterior siding (fiber cement like James Hardie or a brick veneer), roofing rated for North Texas hail, and window specs. The framing inspection happens before any drywall goes up, so changes after this point cost real money.
Stage 5: Finishes, final inspection, and handover (weeks 22 through 30)
Insulation, drywall, cabinets, countertops, flooring, fixtures, paint, and trim, then the final inspection and your walkthrough. You’ll choose cabinet grade and finish, countertop material, flooring, and whether the unit gets its own laundry. Most ADU projects we run in Richland Hills land between four and seven months end to end, and the permit review is usually the biggest variable on that clock.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make
A detached ADU is a whole small house, so the spec decisions stack up fast. Here’s where the money and the long-term satisfaction both live.
- Footprint and layout: a compact one-bedroom around 500 to 600 square feet keeps you near the bottom of the range, while a two-bedroom pushing 900 square feet moves you toward the top. Decide this early; it drives everything downstream.
- Exterior siding: fiber cement (James Hardie is the choice most buyers land on) holds paint well through Texas heat and hail, costs more than vinyl up front, and needs less maintenance over a decade. Brick veneer is the premium option and adds real money.
- Cabinetry: stock or semi-custom cabinets from a name line like Wellborn fit an ADU kitchen well without overspending; KraftMaid and full-custom lines push the budget and rarely add rental value in a unit this size.
- Countertops: quartz or a quartz-engineered surface like Cambria gives you durability that suits a rental or in-law suite; laminate saves money but shows wear faster.
- Roofing: class 4 impact-rated shingles cost more than standard architectural shingles but hold up better against the spring hail this area sees. Worth pricing both before you decide.
- Foundation: post-tensioned slab is standard and less expensive; pier-and-beam is the raised-floor alternative that costs more but handles drainage issues on a low lot.
- Utilities and metering: a shared meter with the main house is cheaper to build; a separate meter adds cost but makes the unit easier to rent out or bill separately. You’ll decide this before we trench.
What New Detached ADU Construction Costs in Richland Hills, TX

Expect $45,000 to $130,000 for a detached ADU here. That’s the lead range for a standard single-story unit on an existing lot, and it’s driven by five things more than anything else.
- Size: square footage is the single biggest lever. A 500-square-foot unit sits near the low end; a 900-square-foot two-bedroom pushes toward the ceiling.
- Site conditions: a lot with a low spot, drainage problems, or a long utility run costs more than a level lot close to existing service.
- Utility distance: relocating or extending sewer, water, and electrical from the main house is often the surprise line item. Longer trench runs add cost.
- Material grade: fiber cement siding, quartz counters, and impact-rated roofing all push toward the high end; standard finishes hold the line.
- Permit and engineering scope: a unit that needs its own engineered foundation design and a full plan-review cycle costs more than a simple rectangular box.
Every written estimate we give is line-item, with fixed pricing and no change orders unless you ask for a scope change. Excluded from most estimates: landscaping and sod restoration, new appliances if you add them, fencing around the unit, and any work on the main house. If your project is part of a full Home Additions & ADU in Richland Hills plan, we scope both together so the numbers don’t collide.
See the difference
Before
After
Before
After
Before
AfterWhat Richland Hills Homes Do to This Job
Richland Hills is a small, fully built-out inner-ring suburb where almost nothing is empty land anymore. The housing stock is mostly mid-century single-family: brick ranches and traditional houses from the 1950s through the 1970s, many on post-tensioned slabs or pier-and-beam foundations, and many still carrying their original electrical panels. That matters for an ADU because the new unit’s electrical load often pushes a service upgrade on the main house that the homeowner didn’t plan for. The expansive clay soil across this pocket of Tarrant County shrinks and swells with the dry spells and heavy rains, so foundation design on the ADU has to account for movement, not just dead load. Lot sizes here are tight, and setbacks are the first thing we check because a mature lot in a built-out city doesn’t always leave room for the unit you pictured.
Hail and wind storms get a vote too: impact-rated roofing and durable siding aren’t optional extras on a unit you plan to keep. We work across the Richland Hills area regularly and know how the city’s inspection schedule runs. If you’re also fixing the driveway while the site is torn up, homeowners often pair this with Concrete Driveways & Concrete Work in Richland Hills or Paver Driveways in Richland Hills so the access and the new unit get finished together.
Serving Richland Hills, TX – Our Local Coverage Area
We serve Richland Hills and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions About New Detached ADU Construction in Richland Hills

Plan on four to seven months from permit submission to final inspection. The framing and finish stages usually run eight to twelve weeks; the rest is design, permitting, and foundation work. Call (855) 912-5373 for a timeline specific to your lot.
Yes. A detached ADU requires its own building permit and must pass foundation, framing, rough-in, and final inspections before it can be occupied. We pull the permits and coordinate the inspections for you.
Usually yes, because the unit is fully separate: its own foundation, plumbing, and electrical. The exception is a service upgrade on the main panel, which is common in older Richland Hills homes and adds cost. We check your panel and service size during the site visit.
Expect $45,000 to $130,000 for a standard single-story unit. Size, utility distance, foundation design, and finish grade are what move the number. Call (855) 912-5373 for an exact quote; estimates are free and line-item.
Well, if the foundation and roof are spec’d for it. Impact-rated roofing, fiber cement siding, and an engineered foundation for clay-soil movement are the three things that matter most. Our work is covered by the 730-Day Done Right Promise: if it’s not done right, we make it right.
Get a Free Estimate for Your New Detached ADU in Richland Hills
Call (855) 912-5373 to schedule a free on-site estimate. We walk your lot, measure the buildable envelope, check setbacks and utility locations, and give you a written line-item number with fixed pricing. Calls are answered by a live person around the clock, and our background-checked technicians show up in uniform. No pressure, no vague bids.
Written by the team at Groundwork Construction Co.