New Detached ADU in Keller, TX: What It Takes and What It Costs
A new detached ADU in Keller typically runs $90,000 – $220,000 and takes six to nine months from the first design meeting to the final inspection. The lead range for a compliant detached unit on a Keller lot sits at $45,000 – $130,000 for a modest one-bedroom, and climbs from there with size and finish level. Call (855) 912-5373 to schedule a free on-site estimate.
How we build a detached ADU, stage by stage

The sequence matters more than the sales pitch. Here’s the actual order of work on a Keller detached unit and roughly how long each stage takes.
- Stage 1: Site assessment and lot verification (1 – 2 weeks). We walk the yard with you, confirm setback distances, check utility routing from the main house, and note the black clay conditions under the proposed footprint. You decide the footprint and the door swing between the ADU and the alley or driveway. Any foundation prep gets flagged here rather than mid-build, which is why we push pier planning to the front.
- Stage 2: Design and architectural review (3 – 6 weeks). You approve the floor plan, elevation, roofing profile, and exterior materials that will match your existing home. In Keller’s HOA subdivisions, the architectural review board timeline runs parallel to our drawing package. We submit elevations and finish samples early so an ARB rejection doesn’t stall the permit.
- Stage 3: Permitting and inspections (4 – 8 weeks in Keller). We pull the building permit, then schedule the inspection sequence: foundation, framing, rough-in electrical and plumbing, insulation, and final. You don’t chase the inspector; we do. Permit timing varies with the city’s queue, so this is the stage most likely to slide.
- Stage 4: Foundation and shell (6 – 10 weeks). Grading and drainage corrections come first, then slab or pier work, framing, roofing, and exterior cladding. You pick exterior colors and the door hardware before this stage starts so we’re not waiting on trim.
- Stage 5: Systems, finishes, and final walkthrough (6 – 10 weeks). Electrical, plumbing, HVAC, insulation, drywall, cabinetry, flooring, and paint. You make finish selections at the start of this stage, not the middle. Final inspection closes the job, and the 730-Day Done Right Promise covers workmanship from that point.
Total realistic timeline: six to nine months for a fully permitted unit, with permitting and ARB review eating roughly a third of it. Calls are answered by a live person around the clock, and every technician on the site is background-checked and arrives in uniform.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll actually make (and what each one costs you)
A detached ADU is a small house, so most of the decisions mirror new construction, just compressed. Here’s what we see Keller homeowners weighing.
- Slab versus pier-and-beam foundation. Slab is cheaper and faster but unforgiving on the black clay. Piers cost more up front and handle seasonal soil movement better. Given Keller’s clay, we usually recommend planning for piers or a reinforced slab with drainage corrections.
- Stick-built versus modular shell. Stick-built gives you full design freedom and matching. A modular shell arrives faster but constrains dimensions. Most Keller lots favor stick-built for ARB matching.
- Exterior cladding. Brick veneer matches your existing house and satisfies most Keller ARB standards. James Hardie fiber cement is the practical alternative when you want lower maintenance. Composition shingle roofing matches the existing rooflines.
- Door style and color. HOA rules in Keller’s master-planned subdivisions typically approve specific entry door colors and materials. We submit finish samples to the ARB before ordering, so you don’t eat a rejection.
- Interior finishes. A rental-grade unit uses stock cabinetry and vinyl plank. An in-law unit calls for KraftMaid cabinetry, a Kohler fixture package, and finishes that hold up. The gap in cost is real; the gap in comfort is bigger.
- HVAC and utilities. A mini-split system is the least invasive. A full ducted system runs cleaner but requires more rough-in work. Utility routing from the main house versus a separate meter is a decision with long-term cost implications.
What a New Detached ADU costs in Keller, TX

Plan on $90,000 – $220,000 for a permitted detached ADU in Keller, with the modest one-bedroom end of the range starting around $45,000 – $130,000 depending on how much finish you want. Here’s how the number moves.
| Line item | Typical range |
|---|---|
| Design and architectural review | Included in estimate, varies with complexity |
| Permitting and inspections | Included in written estimate |
| Foundation (slab or pier) | $8,000 – $25,000 |
| Shell, framing, roofing, cladding | $40,000 – $95,000 |
| Electrical, plumbing, HVAC rough-in and finish | $18,000 – $45,000 |
| Interior finishes (cabinetry, flooring, paint, fixtures) | $15,000 – $55,000 |
Five variables push a Keller ADU to the low or high end: size (a 400 sq ft studio versus a 1,000 sq ft one-bedroom), foundation conditions (clay soil and drainage corrections add cost), utility distance from the main house, finish grade (stock versus KraftMaid and Cambria), and permit scope (a fully permitted unit versus an unpermitted shed conversion, which we don’t do).
Every written estimate is line-item and fixed. The number you see is the number you pay. 0% financing for 18 months is available, and projects over $10,000 get $1,000 off. Call (855) 912-5373 for an exact quote; estimates are free.
See the difference
Before
After
Before
After
Before
AfterWhat Keller homes specifically do to this job
Keller’s housing stock is dominated by brick-veneer traditional homes built in the late 1980s through the 2000s in large HOA subdivisions. Most of those master-planned neighborhoods are now hitting the 25 – 30 year mark, which means the detached ADU conversation here is really a second-generation construction conversation. The families in these homes are adding a unit for aging parents or adult children, not building new construction from scratch.
Two forces shape the job. First, the expansive black clay under Keller subdivisions swells hard between wet and dry seasons. We plan foundation and drainage corrections up front because discovering a slab problem mid-build is costly. Second, HOA architectural review is a real gatekeeper in ZIP codes 76248 and 76244. Approved door styles and colors, roofline matching, and quiet operation requirements all go into the submission package before we order a single finish. Our background-checked, uniformed technicians work within your community’s standards and match existing panels so an approval doesn’t turn into a violation. Keller’s hail and heat also mean roofing and exterior equipment choices get scrutinized at the ARB stage; composition shingles matched to your existing roof profile usually clear it. If the deeper lot work calls for a new driveway to reach the unit, homeowners often pair this with our Concrete Driveways & Concrete Work in Keller or Paver Driveways in Keller. This whole effort is part of a full Home Additions & ADU in Keller scope, and we cover the wider Keller area for it. If you’re comparing this to a smaller interior project, our Home Additions & ADU service page lays out the full menu.
Serving Keller, TX – Our Local Coverage Area
We serve Keller and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – New Detached ADU in Keller

Six to nine months from first meeting to final inspection. Permitting and HOA architectural review eat roughly a third of that time, so getting elevations and finish samples to the ARB early protects your schedule. Call (855) 912-5373 for a timeline specific to your lot.
Yes, any habitable detached unit requires a building permit and a full inspection sequence in Keller. Unpermitted units create resale and insurance problems, and we don’t build them. We pull the permit and schedule the inspections.
Not really; a detached unit is a new structure with its own plumbing, electrical, and foundation. The relevant question is utility distance from the main house, which drives cost more than anything else. We map that in the first week.
$90,000 – $220,000 for a fully permitted unit, with modest one-bedroom builds landing around $45,000 – $130,000. Foundation conditions and finish grade are the two biggest levers. Call (855) 912-5373 for a line-item written quote.
Every new detached ADU we build in Keller is covered by the 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something isn’t right, we make it right.